Capital Improvement Project

Capital Improvement Projects

All updates are from Matthew Hill from EMC Inc.

Bethlehem --

MB Mechanical - We continue to monitor boiler #3 for any additional faults. We are currently waiting for the 3 exhaust dampers recommended by Viessmann to arrive. Once those items are received, I will reach out to coordinate scheduling for their installation.

We remain on schedule for MB Mechanical to return on December 22nd to complete the ERV and ductwork installation.

ENE - ENE is still waiting for the IT department to finalize the network connections required to bring the JACE online. Once those connections are established, ENE will return to complete the integration.

Once the new front end is finalized, ENE will begin training. They will also need to return after the ERV installations are complete to integrate the new units into the existing Building Automation System (BAS).

Additional Items - I was onsite Monday to discuss several items with Bryan, and we have put together an action plan to address them. I have been coordinating with several companies throughout the week and have received one quote, with two additional quotes still pending. Once I have received everything, I will compile the information and forward it along for review.

I was also able to transfer the remaining items from the boiler room storage area into the storage container and take final measurements for the information bulletin board. I plan to begin fabrication next week, with the goal of having it installed the following week.

Lafayette --

The unit ventilator issue was resolved last week. DHI and Emerson Swan were onsite, with Modine technical support joining remotely to assist with troubleshooting. It was determined that a factory setpoint had been reversed, which was corrected with the help of Modine technical support. They were able to provide the Swan technician with the necessary password to access the factory settings and walk them through the correction process. The unit was tested following the adjustment and is now operating properly.

I appreciate everyone's patience as we worked through this issue. A special thank you to Dan from DHI for his continued follow-through and dedication in getting this resolved.

I am also working with Axion to coordinate the garage door installation. I reached out this morning to confirm whether they can complete the installation next week and expect to hear back shortly. I will reach out to Terry as soon as I have confirmation.

Profile --

Presby Energy

The vaporizer installation is scheduled for next Tuesday and Wednesday. The crew will be completing the installation and running the required piping, with final connections scheduled for Wednesday. I spoke with Joe Wood this morning, and he plans to be onsite later Wednesday morning to inspect the completed work.

On Wednesday, Adam will be onsite to temporarily shut down the boilers and bring them back online once the propane connection has been restored. He is also hopeful that the actuators he ordered will arrive in time to replace the units he identified as inoperative in several classrooms experiencing overheating issues.

Andy Bartz has also been notified of the work schedule and will return to complete the final electrical connections to the vaporizer.

MB Mechanical

Boiler Room - MB Mechanical is currently waiting for the replacement parts needed to address the circulator pump issue. Once the parts arrive, I will coordinate their return to complete the repairs.

In the meantime, the two remaining boilers have more than enough capacity to meet the school's heating demands while we work through this unforeseen issue.

Rooftop Units - The rooftop unit installations have been postponed until next spring due to significant supply-chain delays. Nationwide shortages of larger ERVs and air-handling units, driven in part by increased demand from data center construction, continue to impact equipment availability and lead times across the industry.

Four rooftop units are currently scheduled for delivery in January, while RTU-1 is scheduled to arrive in August. We are continuing to work with the supplier to determine whether delivery of RTU-1 can be expedited.

Our plan is to begin installation in early spring, once weather conditions improve and snow has cleared from the roof areas. I will continue monitoring delivery schedules and coordinating with MB Mechanical to get the work scheduled as soon as the equipment becomes available.

ENE / BAS - ENE continues working on the graphics and programming for the new Building Automation System (BAS) front end. They anticipate completing this portion of the project within the coming weeks.

This final phase involves a considerable amount of detail and programming, and I appreciate everyone's patience as ENE works through the remaining items to get the system finalized.

HVAC project

Projects Completion

Bethlehem -- ~70% of project complete

HVAC (MB Mechanical) ~70%

ERV (MB Mechanical) 0%

BAS (ENE) ~70%

Propane (Presby Energy) 100%

Building Envelope (Axion) 100%

Lafayette -- ~95% of project complete

HVAC (DHI) ~99%

BAC (ENE) ~99%

Roofing (KWS) 100%

Exterior (Ridgeline) 100%

Weatherization (Axion) ~90%

Profile -- ~65% of project complete

HVAC (MB Mechanical)

Boiler Room ~99%

Rooftop Units - 0%

BAS (ENE) ~99%

Propane (Presby Energy) ~95%

Building Envelope (Axion) 100%

Files & Folders

Name
Loading...

If contents fail to load, please reload page.

Dates may change as the projects proceed

November 2026
Sun
Mon
Tue
Wed
Thu
Fri
Sat
 Loading events...
November 2026
Sun
Mon
Tue
Wed
Thu
Fri
Sat